Lee's Summit Driveway, Sidewalk, and Concrete Permit Guide for Homeowners
A plain-English summary of published City of Lee's Summit pages for driveway, sidewalk, approach, and patio work. Last checked November 2026.
How to use this guide
This page restates rules the City of Lee's Summit has published for homeowners planning concrete work, and it links to those official pages. It is not legal advice, and it does not replace a conversation with the city about your lot and scope of work. Requirements can change. The links and fees below were last checked in November 2026. Before you demolish a slab, cut a curb, or schedule a pour, confirm the current rules with Lee's Summit Development Services at 816.969.1200 or devtech@cityofls.net.
Start with the city, then your homeowners association
City permits and homeowners association or architectural-review approvals are separate. The official city permit and inspection pages reviewed for this guide do not publish a citywide HOA rule. If your property is in an association, check that association's own guidelines and timeline as well.
How to ask about your specific project
The city's Construction Permits page states that permits may be obtained by a licensed contractor or by a homeowner for their primary residence only. Building permits for commercial, residential, and miscellaneous projects are available online or in person at the Development Services Department, on the first floor of City Hall.
That page directs questions to Development Services at 816.969.1200 or devtech@cityofls.net. Payment options listed by the city include check or credit card online, and check, cash, or credit card in person, with checks payable to the City of Lee's Summit. The online path is the CityView portal linked from the city's permit pages.
Building permits: what the city actually lists
The Building Permits page says Lee's Summit requires building permits for most construction, alteration, repair, and installation projects. Permits are issued for commercial work, residential work, and smaller or limited-scope work classified as miscellaneous permits. Requirements vary by type, size, and complexity.
The published lists are more specific. The residential building permits page states that permits are required to build or replace or repair covered decks and patios, and that permits are required to build or replace or repair decks when the floor surface is more than 30 inches above the adjacent ground level. The miscellaneous building permits page covers other limited-scope work, such as irrigation in the right-of-way, roofing, and utility repairs.
Those lists do not include a standalone category titled driveway, sidewalk, or uncovered patio. This guide does not treat that omission as a yes or a no. Ask Development Services to review the exact work you have in mind, including whether the approach or sidewalk crossing is part of the job.
Right-of-way and the connection to the street
The street connection is where many driveway and sidewalk projects leave private property. The Right-of-Way Permit page states that a right-of-way permit must be obtained from Public Works anytime an excavation is made in the public right-of-way. The city describes the right-of-way as generally a public easement, and says it is generally 10 to 15 feet behind the edge of the street or curb. That is a general description, not a survey of your lot. Apply through the CityView portal described on that page. Inspectors can meet on site if you call ahead. Some activities may also require a Temporary Traffic Control Permit. Questions: Public Works at publicworks@cityofLS.net or 816.969.1800.
Published right-of-way and traffic-control fees
Read fees from the city's schedule rather than estimating a typical driveway total. The Public Works Fees page and the right-of-way permit page list these amounts as effective July 1, 2026, which were the current published figures at the November 2026 check:
- Right-of-way permit: $100.00 per unit. The city defines a unit as one block or 660 feet of continuous linear boring or excavation, or a temporary obstruction.
- Additional right-of-way fees: $100.00 per street cut and $100.00 per street crossing.
- Temporary traffic control permit: $75 for sidewalk, parking, or lane closure or closures; or $110 for land or road closure or closures with a detour and/or special terms or conditions.
Public Works can tell you which of those fees apply to your work.
Inspections if a building permit is issued
The Inspection Process page explains that, upon issuance of a building permit, certain inspections are required. One listed inspection is Driveway/Sidewalks. That inspection “shall be made after all forms and reinforcing steel are in place, but prior to the placement of concrete.” As applicable, manholes, valve boxes, and other equipment shall be adjusted in accordance with the Design and Construction Manual prior to approval.
You can schedule inspections and view reports through the CityView portal linked from that page. If a building permit is issued, plan the pour around the pre-concrete inspection. The Design and Construction Manual is the document the inspection page cites for those field adjustments.
Land disturbance and state permits
The Land Disturbance Permit page states that the city requires any public or private entity that causes or intends to cause a condition that allows for soil erosion — denuding of ground, stockpiling or storing of dirt, or covering the ground with dirt — in an area or areas greater than 2,000 square feet to obtain a Land Disturbance Permit. The application is submitted to Development Services with the appropriate fee and an erosion and sediment control plan prepared in accordance with the Design and Construction Manual.
For projects one acre or greater, the city states that the Missouri Department of Natural Resources may require a separate permit, and directs applicants to 800.361.4827 or the MDNR ePermitting website. Do not assume a typical residential driveway automatically exceeds 2,000 square feet. Measure the area that will actually be disturbed, including removal, stockpiles, and grading, and ask the city if you are close to the limit.
Access, driveway location, and the Unified Development Ordinance
Access rules matter most if you are widening an entrance, adding a second drive, or creating a new street connection. The city's Access Management Code page explains those standards. The official code document linked from that page, revised March 2018, includes these subdivision access rules: direct residential driveway access to individual one-family and two-family dwellings shall be avoided from any arterial or collector street; and residential corner lots shall obtain access from the street with the lowest functional classification, placed as far from the intersection as possible (Access Management Code, PDF, revised March 2018).
Lee's Summit also regulates site standards through its Unified Development Ordinance. Start with the city's Unified Development Ordinance page. This guide does not quote a specific driveway section, because the official hosted ordinance text could not be reliably retrieved during research. If you are changing width, location, or surface, ask Development Services whether any ordinance standards apply, and read the current text from that city page.
A simple sequence before you schedule the pour
- Confirm the property is in the City of Lee's Summit, not only that it has a Lee's Summit mailing address.
- Ask Development Services whether a building or miscellaneous permit applies to your exact scope.
- Determine whether any excavation, material storage, or construction will be in the public right-of-way. If it will, plan a Public Works right-of-way permit and ask whether temporary traffic control is also required.
- Estimate the disturbed area against the city's 2,000-square-foot land-disturbance rule, and ask about state requirements if the project is one acre or greater.
- If a building permit is issued, schedule the driveway and sidewalk inspection after forms and reinforcing steel are in place and before concrete is placed.
- If the property has an HOA, request that association's written approval on its own calendar, which may be earlier than the city's inspection date.
If you have a question about this homeowner guide after the city requirements are clear, you can use the contact page. The City of Lee's Summit, not this guide, is the authority on permits and inspections. Last checked: November 2026. Related: concrete driveways and concrete walkways.